Jacketed Egg Storage Tanks – 40,000 Litres of Additional Working Capacity

How Process Plant Network engineered and supplied two 20,000-litre jacketed, agitated tanks to support expansion at an egg processing facility in Queensland.

2 × 20,000 L
Working capacity per tank
40,000 L
Additional egg storage

1. The Client Brief & Challenge

An egg processing company in Queensland needed additional storage capacity to support production expansion. Fresh liquid egg required chilled holding, gentle agitation and equipment designed for thorough cleaning.

  • Additional capacity: Supply two tanks, each with 20,000 litres of working capacity, to expand egg-holding capacity.
  • Temperature and product handling: Provide jacketed storage suitable for glycol cooling, with agitation to help maintain an even temperature and prevent separation.
  • Hygienic construction: Use stainless steel construction, carefully finished welds and clean-in-place provision for the egg application.
  • Structural design: Engineer the tank supports and vessel construction for the substantial filled load.

2. The Process Plant Network Solution

PPN engineered two jacketed mixing and storage tanks to match the customer’s egg-handling requirements. The tanks operate independently and are positioned alongside one another. Design development included revised drawings and 3D visualisation shared with the customer.

Dimple jackets provide for glycol circulation, while insulation and stainless steel cladding help limit heat gain. Gentle agitation supports even cooling and helps prevent separation. Rotary CIP spray balls provide for internal cleaning after the tanks are emptied.

System Equipment Composition

New Equipment

  • Two 20,000 L working-capacity jacketed, insulated storage tanks with stainless steel cladding.
  • Top-mounted stirrers with motors and gearboxes.
  • Rotary CIP spray balls for internal cleaning.
  • Manhole access, breather ports and engineered supports.

Customer-Supplied Equipment

  • Provision for a customer-supplied bottom stirrer; PPN supplied the top-mounted stirrer.

3. Implementation & Timeline

Design development & approval

PPN developed and revised tank drawings with the customer and used 3D visualisation to review the configuration before manufacture.

Tank fabrication & delivery

PPN fabricated and delivered the two tanks following drawing approval.

Customer-led installation

The customer used its own installation crew and handled the electrical and control work. PPN supplied the tanks; this project did not include PPN installation.

4. Results & Business Impact

  • 40,000 L additional working capacity: Two 20,000-litre tanks expanded the customer’s capacity to hold fresh liquid egg.
  • Support for production expansion: The additional holding capacity supports the customer’s plans to handle and supply more egg product.
  • Designed around the product: Jacket cooling, agitation and CIP provision address the storage and cleaning requirements described in the customer brief.